EPBC Act pre-construction conditions
CONDITION |
EPBC PRE-CONSTRUCTION CONDITION SUMMARY |
COMPLIANCE METHODOLOGY |
1B |
Document As Built Condition of Forecourt Document the as-built condition of the existing handrail, forecourt, entry stairs, entry paving and sandstone bastions and provide this documentation to the Minister prior to commencement of construction. |
Condition 1B was met through delivery of a photographic PDF dilapidation report of the forecourt area and of a ‘360 degree virtual tour’ of the Memorial’s Campbell site to the Department. |
5 |
Archival Recording of AWM Site To minimise the impact of the action on protected matters, prior to the commencement of construction, the approval holder must:
5A) Prepare photographic archival record of existing site and publish to AWM website as a minimum; 5B) Commence a research project to document pubic interpretation of site to record architectural development of site and complete within 12 months of commencement of construction; and 5C) Commence a research project on public memories of Anzac Hall from designers, veterans and visitors and make publicly available within 12 months of commencement of construction. |
Condition 5A has been met through the online publication of a photographic PDF dilapidation report and through the capture and publication of a ‘360 degree virtual tour’ of Anzac Hall: The pre-commencement component of Conditions 5B and 5C has been met through the engagement of a Cultural Heritage & Museum Studies scholar to prepare the two research projects.
The scope of works for this research has been provided to DAWE to demonstrate its suitability, a copy is available to view here: Architectural History of the Memorial - Detailed Statement of Requirement.pdf The final reports will be published to the Memorial’s website no later than June 2022. |
6 |
Updated Heritage Impact Assessment |
The Memorial has engaged Hector Abraham Architects to prepare a Heritage Impact Assessment (HIA) of the project. The HIA was approved by DAWE in December 2020 as part of the project approval process. The HIA is regularly updated to reflect minor design changes made in consultation with the Department and National Capital Authority as part of the approvals process. The current version of the HIA is published below to meet this condition: Heritage Impact Statement Jun-21 [45 MB PDF] |
14 |
Final designs Must finalise design for the specific elements detailed below prior to commencement of construction of these elements and notify Department of final specifications.
|
Condition 14 will be met through approval of the final design of these elements by the National Capital Authority under the Memorial’s ‘main works’ approval. This consultative process is expected to commence in June 2021 and be complete by Q1 2022.
|